345/161kV Switch Yard Area Civil Construction and Auxiliary M&E Project, Hsinta Power Plant Gas Turbine Renewal Construction Project
LocationKaohsiung City, Taiwan
345/161kV Switch Yard Area Civil Construction and Auxiliary M&E Project, Hsinta Power Plant Gas Turbine Renewal Construction Project
2021.5Commenced
LocationKaohsiung City, Taiwan
NT$1,899,596,311
ClientTaiwan Power Company
Taoyuan City Ta-Yuan Urban Planning Project
LocationTaoyuan County, Taiwan
Taoyuan City Ta-Yuan Urban Planning Project
2020.12Commenced
LocationTaoyuan County, Taiwan
NT$1,189,272,682
ClientOffice of Public Construction, Taoyuan
Hsinta Thermal Power Plant Reconstruction Program
LocationKaohsiung City, Taiwan
Hsinta Thermal Power Plant Reconstruction Program
2020.01Commenced
LocationKaohsiung City, Taiwan
NT$7,398,300,000
ClientTaiwan Power Co., Ltd Nuclear Power Generation Department
Repair and Training Practicing Workshop Buildings of Linkou Training Center Power Plant Auxiliary System
LocationLinkou, Taoyuan City, Taiwan
Repair and Training Practicing Workshop Buildings of Linkou Training Center Power Plant Auxiliary System
2019.12Completed
LocationLinkou, Taoyuan City, Taiwan
US$52,125,000
ClientTaiwan Power Company
Package 3 & 4 of Land Readjustment Project Phase 13 in Taichung City
LocationTaichung City, Taiwan
Package 3 & 4 of Land Readjustment Project Phase 13 in Taichung City
2019.11Completed
LocationTaichung City, Taiwan
US$33,626,666
ClientMinistry of Interior
TSMC F18P1 plant building construction project
LocationTainan City
TSMC F18P1 plant building construction project
2019.4Completed
LocationTainan City
NT$1,718,000,000
ClientTaiwan Semiconductor Manufacturing Company
Airport MRT A7 Station Zone Industrial Zone Zone-A Public Works Project
LocationLinko, Taoyuan City
Airport MRT A7 Station Zone Industrial Zone Zone-A Public Works Project
2018.5Completed
LocationLinko, Taoyuan City
NT$438,095,238
ClientPlant Building for Chroma ATE Inc. & Heyang International & Shunda Technology
Civil and Foundation Associated Works for the Installation of Unit #1 / #2 GSG in Dah Tarn Power Plant
LocationTaoyuan City, Taiwan
Civil and Foundation Associated Works for the Installation of Unit #1 / #2 GSG in Dah Tarn Power Plant
2017.12Completed
LocationTaoyuan City, Taiwan
US$8,620,000
ClientCTCI Corporation
Package 4 of Zone Expropriation Civil Works in Airport MRT Access A7 Station District
LocationLinkou, Taoyuan City, Taiwan
Package 4 of Zone Expropriation Civil Works in Airport MRT Access A7 Station District
2017.11Completed
LocationLinkou, Taoyuan City, Taiwan
US$43,312,500
ClientMinistry of Interior
Construction of Intake Area for CV07A Circulating Water System, Talin Power Plant Renovation Project
LocationKaohsiung City, Taiwan
Construction of Intake Area for CV07A Circulating Water System, Talin Power Plant Renovation Project
2016.11Completed
LocationKaohsiung City, Taiwan
US$24,312,500
ClientTaiwan Power Company
Civil Works, Talin Power Plant Units 1 & 2 Renewal Project AQCS/MEEB/EDG Facilities
LocationKaohsiung City, Taiwan
Civil Works, Talin Power Plant Units 1 & 2 Renewal Project AQCS/MEEB/EDG Facilities
2013.7Completed
LocationKaohsiung City, Taiwan
US$27,234,508
ClientCTCI Corporation
Civil Works, Talin Power Plant Units 1 & 2 Renewal Project Unit 1 & 2 Steam Generator House
LocationKaohsiung City, Taiwan
Civil Works, Talin Power Plant Units 1 & 2 Renewal Project Unit 1 & 2 Steam Generator House
2013.6Completed
LocationKaohsiung City, Taiwan
US$7,611,315
ClientCTCI Corporation
Package B of UMC FAB12A P5/P6 Building and Architectural Works
LocationTainan City, Taiwan
Package B of UMC FAB12A P5/P6 Building and Architectural Works
2012.8Completed
LocationTainan City, Taiwan
US$19,218,750
ClientUnited Microelectronics Corporation
Civil Works for Continuous Annealing Coating Line of Non-directional Silicon Steel Production
LocationKaohsiung City, Taiwan
Civil Works for Continuous Annealing Coating Line of Non-directional Silicon Steel Production
2011.11Completed
LocationKaohsiung City, Taiwan
US$7,390,625
ClientChina Steel Corporation
Low Radiation Waste Storage Construction in Long-Men (The 4th Nuclear Power) Project
LocationGongliao, New Taipei City, Taiwan
Low Radiation Waste Storage Construction in Long-Men (The 4th Nuclear Power) Project
2011.6Completed
LocationGongliao, New Taipei City, Taiwan
US$21,656,250
ClientTaiwan Power Company
Civil Works of Coal Yard, Temporary Coal Supply Facilities of No. 1 & 2 Generator Sets, Talin Coal-fired Power Plant
LocationKaohsiung City, Taiwan
Civil Works of Coal Yard, Temporary Coal Supply Facilities of No. 1 & 2 Generator Sets, Talin Coal-fired Power Plant
2010.11Completed
LocationKaohsiung City, Taiwan
US$9,638,872
ClientTaiwan Power Company
Structural Works, Datan Power Plant Generator Installation
LocationGuanyin, Taoyuan City, Taiwan
Structural Works, Datan Power Plant Generator Installation
2009.10Completed
LocationGuanyin, Taoyuan City, Taiwan
US$22,804,688
ClientMitsubishi Heavy Industries / CTCI Corporation
Civil & Architectural Works of RFCC Plant Construction, Turnkey Project of Residue Fluidized Catalytic Cracking (RFCC) in Talin Petroleum Refinery Plant for Chinese Petroleum Corp.
LocationKaohsiung City, Taiwan
Civil & Architectural Works of RFCC Plant Construction, Turnkey Project of Residue Fluidized Catalytic Cracking (RFCC) in Talin Petroleum Refinery Plant for Chinese Petroleum Corp.
2009.5Completed
LocationKaohsiung City, Taiwan
US$13,717,133
ClientCTCI Corporation
Civil Works, Chinese Petroleum Corp.Liquefied Natural Gas (LNG) Reception Station
LocationTaichung Harbor, Taiwan
Civil Works, Chinese Petroleum Corp.Liquefied Natural Gas (LNG) Reception Station
2007.12Completed
LocationTaichung Harbor, Taiwan
US$9,753,902
ClientCTCI Corporation
Civil Works of New Steel Mill Expansion Project, Phase II
LocationTaichung Harbor, Taiwan
Civil Works of New Steel Mill Expansion Project, Phase II
2006.12Completed
LocationTaichung Harbor, Taiwan
US$38,985,996
ClientChina Steel Corporation
ASE Group wafer Packaging Plant Construction Project (Construction Management)
LocationKaohsiung Export Processing Zone
ASE Group wafer Packaging Plant Construction Project (Construction Management)
2001.6/2004.7Completed
LocationKaohsiung Export Processing Zone
A:
NT$13,991,000
B:
NT$8,653,050ClientConstruction Management for ASE Group/Acer Construction/Fu Hua Engineering
ASE Group wafer Packaging Plant Construction Project
LocationChungli Industrial Zone
ASE Group wafer Packaging Plant Construction Project
2004.7Completed
LocationChungli Industrial Zone
NT$383,874,466
ClientConstruction Management for ASE Group/Acer Construction/Fu Hua Engineering
Taichung Fossil Power Plant Units 9 & 10 Flue Gas Desulphurization (FGD) Plant
LocationTaichung Harbor, Taiwan
Taichung Fossil Power Plant Units 9 & 10 Flue Gas Desulphurization (FGD) Plant
2002.11Completed
LocationTaichung Harbor, Taiwan
US$6,974,816
ClientIshikawajuma Harima Heavy Industries (IHI), Japan